11 June 02 Empennage kit arrives.
24 Dec 02 Received the letter from the
Feds. Officially have "N303P" reserved.
24 Dec 03 Finally got the letter from
Vans, wing delivery scheduled for week of 10 Feb 03.
7 Nov 02 Generally done with empennage
metal work
4 Dec 02 Finished Empennage! Total of
164.65 hours to date.10 Dec 02 Tail Inspection by IA
3 Feb 03
Wing kit arrives
11 Oct 03 Finish Left Tank & pressure
test
22 Nov 03 Start Ailerons
3 Jan 04 Both ailerons
completed
28 Feb 04
Left wing complete
6 Mar 04 Both flaps complete
14 Mar 04
Re-start right wing.
Spars already complete.2 Apr 04
Start right tank.
6 Jun 04 Put the fuselage
order in the mail.20 Jun 04 Finish pressure
testing right tank.
24 Jul 04
Complete right wing.
9 Aug 04 Sent final payment
to Vans for the fuselage kit. Due to be shipped week of Sept 6th.
13 Sep 04
Received Fuselage
Kit.21 Nov 04 Complete Bulkheads
28 Jan 05
Generally done with
center section.30 Apr 05
Rolled the Fuselage
over.
12 May 05 Received
confirmation that finish kit ships week of July 18th.
26 Aug 05 Started re-location
proceedings in June 05. No progress on RV until move is complete and shop
is set up.
26 Nov 05
Fitted the wings to
the fuselage28 Nov 05 Finish kit scheduled
for delivery!
12 Dec 05
Started back on the
fuselage after the relocation4 April 06
Started work on the
canopy
16 Mar 07 Engine Delivered |